This Thursday, the City Council of Ciudad Real, together with the City Council of Migueltura and the Spanish Basin State Water Company (Aquaes), announced the mark before and after« In water hygiene management … and in the modernization of the hydraulic systems of both locations. Serving approximately 100,000 residents.
Ciudad Real Mayor Francisco Cañizares said:It’s an important day for Ciudad Real and for Migueltura.”, he stressed that the agreement “answers one of the major concerns of recent years.” water hygiene», as reported by the City Council of Ciudad Real in a press release.
Coach Cañizares explained: The contract envisages an initial investment of 1.5 million euros for the drafting of the technical project, which will then be submitted to tender.. “This is the first step on a decisive path to solving the structural problems of our cities and federations,” he stressed, stressing that this is a joint effort that will require the support of the European Fund, the Spanish Government, the Regional Commission and the State Parliament.
In addition, the provincial mayor emphasized that the project will improve wastewater treatment, ensure orderly growth of the city and strengthen the city’s commitment to environmental protection.
María Rosa Cobo, President of the Aquaes Municipal Board, emphasized the importance of this new phase of cooperation between the two towns and the state society. Cobo recalled that this relationship dates back to 2005, when the first agreement was signed with Hydrogudiana, which made it possible to invest more than 50 million euros in the expansion of the Ciudad Real sewage treatment plant and the general sanitation system.
20 months for project approval
Kobo specified that the signed agreement will allow for the drafting of construction projects necessary for the deployment of the main collector, the construction of new surrounding collectors and the construction of rainwater tanks. As it progresses, The contract specifications for these services, with a budget of EUR 1,395,000 and an execution period of 16 months, will be immediately uploaded to the public procurement platform..
The president estimates that: Within about 20 months, the project will be approved and ready for execution. Material and decisive financing.